Services Infrastructure Capacity & Compliance Assessment

Gold Coast City Council (GCCC) own nine beach front  tourist parks which cater for camper vans, tents, caravans,  long term residents and fixed abode high spec holiday  homes. As part of the GCCC tourist parks expansion, development and upgrade plans, was a proposal to built additional holiday homes.

Understanding this would have an effect on the services;  the starting point for the council was to determine the  existing services infrastructure capacity of the parks.

NDY was engaged to:

  • Carry out assessments to confirm existing infrastructure layouts
  • Carry out assessments to determine existing available capacities
  • Report on the compliance of the existing services and provide recommendation on any upgrades required to meet Australian Standards
  • Assess the councils planned site developments to determine and specify any infrastructure upgrades required to meet their needs.

The following services were assessed:

Sewer and Septic Systems

This assessment involved determining the capacity of each  pipe/septic tank in the system, its existing usage, its  proposed additional loading and upgrades required to  meet this loading demand.

Domestic Cold Water and Gas

A flow and pressure assessment revealed upgrades  needed and required rerouting of these service to meet  planned developments.  Valving and isolation compliance  recommendations were also provided.

Stormwater

Rainfall catchment assessments and the proposed sealing  of unsealed surfaces where the main focus of this  component of the project.  This allowed us to determine  required upgrades to the existing systems.

Fire Protection

The level of maintenance, valving and user ability of fire  hose reels and hydrants was assessed as well as the  extent of their reticulation system. This allowed compliance  issues be flagged consequently rectified.

Electrical and Telecommunications

An assessment of the service providers local capacity was  undertaken prior to determining the available on site  capacity and required compliance upgrades. Following the assessments, GCCC were provided with a  complete set of reports and drawings detailing the findings  of each assessment.  This allowed GCCC to confidently  progress the planned developments understanding the  restraints of their existing systems and the required  upgrades.  The assessment results also furnished GCCC  with the details of the compliance upgrades required.

Project Details

Market Sector:
Asset Performance

Client: Gold Coast City Council

Location:
Australia
QLD